In short: A certificate of design compliance (CDC) is the BA3 certificate in which an independent building surveyor states that a building, if completed to the plans and specifications it lists, will comply with each applicable building standard. In WA it comes with a certified building permit application, or the permit authority arranges it for an uncertified application, which is only open to Class 1a and Class 10 buildings.

Key takeaways

  • A CDC must be signed by a building surveyor who is not the owner, the builder, or an employee of either.
  • Certified applications can be made for any building class; uncertified ones only for Class 1a houses and Class 10 structures.
  • The permit authority has 10 business days to decide a certified application and 25 for an uncertified one, unless longer is agreed in writing.
  • Building and Energy says a building surveyor must scrutinise every technical document, such as an engineer's certificate or report, before relying on it.
  • A building permit that sets no period has effect for 2 years from the day it is granted.
Rolled and flat construction drawings, a white hard hat and a tape measure on a timber trestle table at a house site, with tan brick walls and scaffolding rising from a concrete slab on pale sand behind

Need structural drawings or engineering certification for a building permit in Perth or Mandurah? Send us your plans for a quote, or call 1300 614 803.

What is a certificate of design compliance?

A certificate of design compliance (CDC) is the certificate in which a building surveyor states that a proposed building, if completed in accordance with the plans and specifications listed in it, will comply with each applicable building standard. Section 19 of WA's Building Act 2011 requires that statement, and requires the certificate to be in an approved form. The approved form is the BA3, approved by the Building Commissioner on 10 April 2025.

The BA3 form lists the building's class under the Building Code of Australia (BCA), the edition of the Building Code applied, the drawings, specifications and technical documents it covers, and the inspections and tests prescribed for the work.

A CDC is a design approval step, not a building permit. Section 9 of the Act says building work must not be done unless a building permit is in effect for it, or the work is exempt.

Who issues a certificate of design compliance in WA?

A certificate of design compliance is signed by a registered building surveyor who is independent of the job. The WA Government says local governments and registered building surveying contractors can issue a CDC, and that one is required before a building permit is granted. Under section 4 of the Building Act 2011, an independent building surveyor is neither an owner of the land, the builder named on the permit, nor an employee of either.

The WA Government's register of building surveyors says a compliance certificate must be issued by a registered building surveying contractor, or by a registered building surveying practitioner employed by a local government or other permit authority. Other registered practitioners cannot issue them.

Building and Energy's Industry Bulletin 144 says building surveyors are wholly responsible for the compliance certificates they sign.

What is the difference between a certified and an uncertified application?

A certified building permit application is lodged with a CDC already signed, while an uncertified application is lodged without one and the permit authority arranges the certification.

Certified application Uncertified application
Form BA1 BA2
Buildings it can be used for Any class of building Class 1a and Class 10 buildings and incidental structures only (Building Regulations 2012, regulation 15)
Who arranges the CDC The applicant engages a building surveyor before lodging The permit authority refers the application to a building surveyor (section 17)
What is lodged The CDC and the plans and specifications it lists (section 16) The plans and specifications, for the building surveyor to consider
Time to decide 10 business days 25 business days
Application fee, Class 1 or 10 0.19% of the estimated value of the work, minimum $121.00 0.32% of the estimated value of the work, minimum $121.00

The fees come from Building and Energy's building approvals page. The City of Cockburn's building permit page says a certified application is mandatory for Class 2 to Class 9 buildings, such as shops, apartments, warehouses and offices.

What engineering documents does a certificate of design compliance rely on?

A certificate of design compliance can rely on engineers' drawings, certificates and reports, listed in Part 3 of the BA3 form with the plans, specifications and technical documents. Industry Bulletin 144 says "technical documents" generally means any supporting document that supplements, or is part of, the plans and specifications as evidence of compliance with the building standards.

Industry Bulletin 144 says the building surveyor must scrutinise every technical document before relying on it. Surveyors are not expected to check complex calculations, but must check the basic assumptions and inputs, that the document is fit for purpose, and the competency of its author. Quoting the Australian Building Codes Board's Evidence of Suitability Handbook, the bulletin says an engineer's certificate or report should set out the basis of its verification in a form that can be scrutinised, and reference the standards, specifications and software relied on.

Councils publish their own lists. The City of Cockburn's submission checklist for Class 1 and Class 10 buildings (March 2020) asks for these structural items:

Item What the City of Cockburn checklist asks for
Structural drawings, specifications and details Certified by a structural engineer, or shown to meet the BCA deemed-to-satisfy provisions
Site report Site or soil classification, with recommendations for earthworks, foundations and drainage
Footing and slab details Concrete specification, strip and pad footing sizes, reinforcement and slab thickness, with engineer certification for a slab under the deemed-to-satisfy 100 mm
Structural beams Designed by a structural engineer, or to the BCA deemed-to-satisfy provisions
Retaining walls Walls 500 mm or more in height designed by a structural engineer
Two-storey construction All structural elements and details certified by a structural engineer
Underpinning Design and specifications by a structural engineer, plus signed BA20 or BA20A consents from affected neighbours

How long does a building permit take in WA?

A WA permit authority must decide a certified application within 10 business days and an uncertified application within 25 business days, or a longer period agreed in writing with the applicant. These periods are set by regulation 20 of the Building Regulations 2012 under section 23 of the Act.

Other rules can stretch the time:

  • Further information. Under section 18, the permit authority may ask for documents or information within a specified time of no more than 21 days, and may refuse to consider the application if they are not given. Once the request is met, only the balance of the decision period remains.
  • Planning approval. For an uncertified application where the work needs development approval, regulation 20 excludes the days between lodging the development application and its decision.
  • No decision in time. Section 23 says the permit is then taken to be refused, and the application fee must be refunded, although the authority may still decide later.

Once granted, a permit has effect for the period it sets out. Section 32 says a permit that sets no period has effect for 2 years from the day it is granted.

Building permits in Perth: the WA rules

In Perth and Mandurah, the building permit usually comes from the local government, which Building and Energy's Building Act 2011 overview calls the main permit authority. Building and Energy, a division of the Department of Local Government, Industry Regulation and Safety, publishes the BA forms the Building Commissioner approves.

Before granting a permit, the permit authority must be satisfied of every matter in section 20 of the Act. For work that is development under the Planning and Development Act 2005, regulation 18 makes each planning approval a prescribed authority, and regulation 16 requires a certified application to include evidence that it has been obtained.

Work near a boundary can need a neighbour's consent on form BA20, or a court order, if it encroaches on or may adversely affect other land (sections 20, 76 and 77; regulation 16(3)). The overview says that in the vast majority of applications that consent will not be required, and that a statement from a registered builder, building surveyor, engineer or architect that there are no adverse effects can be attached to the application.

When to call a structural engineer

Call a structural engineer before you apply for a building permit when the building surveyor or council needs engineering evidence. Call one if:

  • you are building a new home, a granny flat or a two-storey house;
  • you are removing a load-bearing wall or pillar and need a beam designed;
  • a retaining wall is 500 mm or more in height (the City of Cockburn's checklist asks for an engineer's design from that height);
  • your excavation or footings sit near a boundary and you need a statement on effects to the neighbour's land;
  • the building surveyor has asked for more structural information during assessment.

Our structural engineering services include footing and slab design, beam design for renovations, retaining wall design and structural certification. A structural engineer's documents support the building surveyor's assessment; the building surveyor signs the CDC. For retaining wall permits, see our guide to limestone retaining walls in Perth, and for footings on sand, strip footings explained. We cover the suburbs on our service areas page.

Example from our projects

Frequently asked questions

Is there a certificate after the building is finished?

For multi-residential, commercial and public buildings, yes. Building and Energy's overview says these need an occupancy permit, and the application must come with a certificate of construction compliance signed by an independent building surveyor, confirming the building was built in accordance with its permit.

Is there a levy on top of the building permit fee?

Yes. Building and Energy's fee table sets the Building Services Levy on a building permit at 0.137% of the value of the work over $45,000, or $61.65 for work of $45,000 or less, paid to the local government permit authority.

How do I check that a building surveyor is registered in WA?

Download the register of building surveyors from the WA Government's 'Find a registered building surveyor' page, or use its Online Licence Search. The downloadable register lists active and inactive registrations, and inactive entries have a blank address column.

What if my building permit is about to expire?

Apply to the permit authority on form BA22 to extend the time. Building and Energy's Industry Bulletin 152 says the application can be made before or after the expiry day, and the permit keeps effect while it is decided.

Sources

  1. Building and Energy: Building Act 2011 overview (fact sheet)
  2. Building Act 2011 (WA), sections 4, 9, 14, 16 to 20, 23, 32, 76 and 77
  3. Building Regulations 2012 (WA), regulations 15, 16, 18 and 20
  4. Building and Energy: Form BA3, Certificate of design compliance (approved 10 April 2025)
  5. Building and Energy: Industry Bulletin 144, Technical documents (March 2022)
  6. Building and Energy: Industry Bulletin 152, Duration of building permits (June 2023)
  7. Building and Energy: Building approvals (forms and fees)
  8. WA Government: Find a registered building surveyor